If its broken, we can fix it.
If you need it, we can make it.

History of CCA
|
June 27th 2004 We begin with nothing but a marked out piece of property and a dream. |
|
July 5th 2004 We begin building concrete forms for 6" thick slab. |
|
July 10th 2004 Finally construction begins on the concrete. |
|
July 18th 2004 The first slab is now complete. |
August 19th 2004 The building frame is now being installed. |
August 25th 2004 3 out of 4 walls are up. |
August 28th 2004 3 1/2 walls up, almost ready for the installation of the roof. |
August 30th 2004 Insulation is being prepared for installation. |
September 18th 2004 Building is complete, and our first machines are brought in. |
|
2005 Building is stocked with machines, welders, equipment and tooling. All 3-phase power, air lines and water lines are installed. |